Procurement thresholds · 2026
Hungarian public procurement thresholds 2026
Quick calculator, national and EU thresholds, and answers to the most common questions. All on one page.
What you'll find
Public procurement threshold checker
When does public procurement become mandatory in Hungary, and would your project need it? Enter the project details and get the answer in seconds.
Applicable (expected) threshold: —
❗ Select the options above to display the threshold.
Public procurement thresholds 2026
From 2026 the procurement threshold depends on the type of procurement. For classical contracting authorities, the national threshold is HUF 20 million for supplies and services and HUF 60 million for works. The EU thresholds are much higher, but the multiple varies sharply by type of procurement: roughly three to four times for supplies and services, and twenty to thirty-five times for works. The European Commission reviews the EU thresholds every two years, while the national thresholds are set every year in the central budget act. If the estimated net value of the planned procurement reaches or exceeds the national threshold, a procurement procedure must as a rule be run under the national procedure, and under the EU procedure if the value also reaches the EU threshold. The obligation also requires the buyer to qualify as a contracting authority and no statutory exemption to apply.
National public procurement thresholds 2026
The national public procurement thresholds set in HUF, valid from 1 January to 31 December 2026. The thresholds are net amounts: the estimated value is calculated without VAT (Kbt. Section 16(1)). At or above the applicable threshold, a public procurement procedure is required as a general rule.
| Type of contracting authority | Supplies | Services | Works | Service concession | Works concession |
|---|---|---|---|---|---|
| Classical contracting authority | 20 000 000 HUF |
20 000 000 HUF |
60 000 000 HUF |
30 000 000 HUF |
100 000 000 HUF |
| Utilities contracting authority | 50 000 000 HUF |
50 000 000 HUF |
100 000 000 HUF |
100 000 000 HUF |
200 000 000 HUF |
| Other publicly funded organisation | 20 000 000 HUF |
20 000 000 HUF |
60 000 000 HUF |
30 000 000 HUF |
100 000 000 HUF |
| Ceiling for a lot that can be split off (Kbt. s. 19(4)(a)) |
80 000 EUR
31 664 480 HUF
|
80 000 EUR
31 664 480 HUF
|
1 000 000 EUR
395 806 000 HUF
|
— | — |
The HUF 30 million national threshold does not apply to service concessions for social and other specific services. For those, a procedure is required from the EU threshold.
EU public procurement thresholds 2026–2027
EU public procurement thresholds by procurement type and value. Once the threshold is reached, a public procurement procedure is required as a general rule. The euro amounts and the forint amounts published by the Public Procurement Authority apply from 1 January 2026 to 31 December 2027.
The EU thresholds are set in SDR by the WTO Government Procurement Agreement (130 000, 200 000, 400 000 and 5 000 000 SDR), and the Commission converts them to euro every two years.
| Type of contracting authority ↓ / Type of procurement → | Supplies | Services | Works | Social and other specific services |
|---|---|---|---|---|
| Classical contracting authority |
216 000 EUR
85 494 096 HUF
EU procedure, TED
|
216 000 EUR
85 494 096 HUF
EU procedure, TED
|
5 404 000 EUR
2 138 935 624 HUF
EU procedure, TED
|
750 000 EUR
296 854 500 HUF
EU "light-touch"
|
| Ministry, designated central purchasing body |
140 000 EUR
55 412 840 HUF
EU procedure, TED
|
140 000 EUR
55 412 840 HUF
EU procedure, TED
|
5 404 000 EUR
2 138 935 624 HUF
EU procedure, TED
|
750 000 EUR
296 854 500 HUF
EU "light-touch"
|
| Utilities contracting authority |
432 000 EUR
170 988 192 HUF
EU procedure, TED
|
432 000 EUR
170 988 192 HUF
EU procedure, TED
|
5 404 000 EUR
2 138 935 624 HUF
EU procedure, TED
|
1 000 000 EUR
395 806 000 HUF
EU "light-touch"
|
For works and services concessions, the EU threshold is EUR 5 404 000 (HUF 2 138 935 624) for every type of contracting authority. For defence goods bought by ministries and designated central purchasing bodies, the EUR 140 000 threshold applies only to goods listed in Annex 2 of the Kbt. Other defence goods fall under the EUR 216 000 threshold.
Sources, from 1 January 2026: notice of the President of the Hungarian Public Procurement Authority on the thresholds applicable from 1 January 2026 (in Hungarian). EU thresholds: Commission Delegated Regulations (EU) 2025/2152, 2025/2150 and 2025/2151, HUF equivalents per Commission notice C/2025/5732. National thresholds: Section 75 of Act LXIX of 2025 and Section 15(3) of the Kbt.
Procurement preparation with expert support
We help you establish the correct threshold and the applicable procedure as early as the planning stage. That way you avoid changes later on, lost time and the risk of an infringement.
If a procedure is needed: how public procurement works in Hungary →
2027 thresholds. The EU thresholds stay unchanged until 31 December 2027. The national thresholds for 2027 will be set by the 2027 central budget act, which has not been published yet. We will update this page as soon as it is promulgated.
What changed between 2024 and 2026?
The procurement thresholds and the related procedural rules were amended in several steps. The timeline below summarises the main changes that affect contracting authorities. The national threshold amounts last changed on 1 January 2025 and are unchanged for 2026. Otherwise the changes concerned the EU values, the range of organisations bound by the obligation and the exemptions in the national procedure.
| Effective date | What changed |
|---|---|
| 1 January 2024 | The EU thresholds rose by roughly 2 to 3 per cent in euro as part of the biennial review. For classical contracting authorities, for example, the supplies and services threshold went from EUR 215 000 to EUR 221 000 and the works threshold from EUR 5 382 000 to EUR 5 538 000. The threshold for social and other specific services did not change. |
| 1 February 2024 | Organisations otherwise outside the scope of the Kbt. must also run a procurement procedure when a service contract reaching the national threshold is financed directly from EU funds. The rule does not cover supplies or works, nor services financed from the Recovery and Resilience Facility (RRF). |
| 1 January 2025 | The exemption ceiling for social and other specific services rose from HUF 30 million to HUF 50 million (Section 111(d) of the Kbt., as amended by Section 63, point 12 of Act LXIV of 2024). This is an exemption ceiling, not a national threshold: the budget act that sets the national thresholds (for 2026, Section 75 of Act LXIX of 2025) sets no separate national threshold for these services. Ancillary procurement services became exempt in the national procedure, up to the EU threshold. |
| 1 January 2026 | The EU thresholds fell by 2 to 2.5 per cent in euro but rose by about 1 per cent in forint, because the fixed conversion rate moved from 382.85 to 395.806 HUF/EUR. The national thresholds are unchanged. |
Aggregation: when do several items count as a single procurement?
When a procurement is split into parts and carried out through several contracts, the value of every part counts towards the estimated value (Section 19(3) of the Kbt.). Which purchases belong together depends on the subject matter:
| Subject of the procurement | What must be counted together |
|---|---|
| Works | Every part of a single works project that forms a technical and economic functional unit. This includes the value of goods and services the contracting authority makes available for the construction. |
| Services | Services aimed at the same direct purpose. This is judged by the technical and economic functional unity of the services. |
| Supplies | Goods intended for the same or similar use. |
Ordering the parts under separate contracts or at different times does not avoid aggregation. If the contracting authority allows tenders for lots, the value of every lot still counts towards the estimated value, so the total value determines the procedure. Above the EU threshold, certain smaller lots can be procured under the national procedure on certain conditions, as explained in this question.
According to the guidance of the Council operating within the Public Procurement Authority (in Hungarian), the main test is technical and economic functional unity. Where that does not settle the question, auxiliary factors help: unified planning and decision-making, the same contracting authority, the same legal basis and contract terms, and a link in time, which does not have to mean simultaneity. The guidance adds that budget planning or a different funding source does not break the unity, and a different place of performance alone does not justify splitting. A need that arises later, separately and unforeseeably can, however, count as a separate procurement.
A practical example from the Public Procurement Authority: if the contracting authority signs one contract for maintaining an IT system and a separate one for custom development of the same system, the two values must be counted together, because both serve the same direct purpose, the proper operation of the system. In case of doubt, it is worth recording the reasons for a decision to split in writing beforehand.
Aggregation is easiest to get right when drawing up the annual procurement plan, because every purchasing need for the year is visible in one place. See our guide to internal procurement rules and the annual plan.
Frequently asked questions about procurement thresholds
In 2026 the Hungarian national thresholds for classical contracting authorities are HUF 20 million for supplies and services and HUF 60 million for works. For utilities contracting authorities they are HUF 50 million for supplies and services and HUF 100 million for works. The EU thresholds are much higher, but the multiple varies sharply by type of procurement: roughly three to four times for supplies and services, and twenty to thirty-five times for works. They also differ by type of contracting authority. All values are net, excluding VAT.
Light-touch is the less formalised EU procedural regime for social and other specific services. These services are listed in Annex 3 of the Kbt. It allows more flexible procedural rules, but the principles of public procurement (equal treatment, transparency, equal opportunity) still apply. Under Hungarian law, these procurements, other than concessions, are run under the rules of the national procedure even above the EU threshold. The thresholds are in the table above, and the changes over time are in the "What changed" table.
Procurement thresholds must always be assessed on net amounts, excluding VAT. The national threshold for classical contracting authorities is therefore HUF 20 000 000. This applies even if the contracting authority is not entitled to deduct VAT. Using the gross amount can lead to the wrong threshold.
In EU procurement the thresholds are likewise set as net amounts, in euro (EUR). You do not need to apply an exchange rate of your own. The forint amounts of the EU thresholds are fixed by a notice of the European Commission and published by the Public Procurement Authority (Section 15(5) of the Kbt.). For 2026 and 2027 they are based on HUF 395.806 per EUR.
Three practical cases often confuse the net rule. For construction services under the reverse-charge scheme, the contract price is net anyway, because the VAT is payable by the customer. The net contract amount therefore goes into the estimated value as a matter of course. With a supplier taxed under KATA (the Hungarian flat-rate tax for small businesses) or exempt from VAT as a small business, the invoice shows no VAT, so the gross tender price equals the net consideration. This difference matters in market research, because for tenders with the same technical content the VAT status can change the basis of comparison. For EU-funded procurements the estimated value is still the net consideration, whatever share of the VAT is eligible under the grant documents.
For indefinite-term contracts, the estimated value must be projected over 48 months. The monthly or annual fee must be multiplied out over four years, and this amount is compared against the procurement threshold. For framework agreements, the thresholds must be assessed on the total framework amount, regardless of the number of suppliers selected. The expected total value of the call-offs determines which threshold applies when establishing the procurement obligation. For multi-year fixed-term contracts, the total value over the whole contract term counts as a rule, even if the values performed in the individual years differ. The exception is a service contract without a total price, such as maintenance paid monthly. For a term of up to four years the fee for the whole term counts, but for a fixed term longer than four years the monthly fee multiplied by 48 applies.
If the estimated net value of the procurement reaches the applicable threshold, the contracting authority is as a rule bound to run a public procurement procedure. This means the contract may only be concluded as the result of a procurement procedure. Reaching the value is necessary but not sufficient on its own. The obligation also requires that the buyer is a contracting authority under the Act, or becomes bound to run a procedure, for example because of EU funding, that the purchase qualifies as a public contract or concession, and that no statutory exemption applies.
The procedure also shapes the timetable. In the national procedure, for open, restricted and negotiated procedures, the time limit for tenders is at least 10 days for supplies and services and at least 15 days for works, counted from the dispatch of the notice or the invitation. The EU procedure generally sets longer minimum time limits. You can check the minimum time limits for tenders under each procedure with our public procurement deadline calculator.
A contract concluded by unlawfully skipping the procurement procedure is null and void (Section 137 of the Kbt.). There are two narrow exceptions. The first applies if the contracting authority did not run a procedure with a prior notice because it relied on a statutory exemption or a procedure without prior publication, published a notice of its intention to conclude the contract in advance, and did not sign the contract within ten days from the day after publication. The second applies if an overriding public interest requires the contract to be performed. Delay, the cost of a new procedure or a change of contractor do not count as such an interest, and other economic interests count only if nullity would have disproportionate consequences.
The Public Procurement Arbitration Board (KDB) decides on nullity of its own motion, and when it finds that a procedure was unlawfully skipped it must impose a fine. The fine is capped at 15 per cent of the contract value.
Close to the threshold, the contracting authority must be prepared to correct course. If the estimated value changes while the procedure is being prepared and crosses the applicable threshold, the steps taken so far must be reviewed and the procurement must move to the procedure that applies at the higher level.
In practice, three risks need to be balanced: starting a procedure that was not needed, the review risk of underestimating the value, and the burden of changing the procedure once the threshold is crossed. All three can be reduced if the method used to calculate the estimated value, its sources and the built-in safety margin are documented in the procurement file. A later audit or review procedure can then also show that the choice of procedure was well founded.
When assessing the threshold, take into account the consideration for the full term of the contract, options and extensions, the maximum framework amount that can be called off, and the value of purchases that must be aggregated. Which purchases must be counted together depends on the subject matter, as explained in the section on aggregation.
Artificially splitting a procurement to stay below the threshold is prohibited.
If the aggregated total estimated value reaches the EU threshold, certain lots can, by way of exception, still be procured under the national procedure. Two conditions must both be met. The net value of the lot on its own stays below EUR 80 000 for supplies and services, or below EUR 1 000 000 for works, and the combined value of the lots split off this way does not exceed 20 per cent of the total estimated value of the procurement.
A concrete example: from a services procurement with a total value of EUR 300 000, lots worth at most EUR 60 000 can be split off, because that is what the 20 per cent cap allows. The EUR 60 000 can be divided into one or more lots. The lots split off do not fall outside the scope of the Kbt.: a public procurement procedure must still be run for them, only under the rules of the national procedure. In that case the exemptions for procurements below the EU threshold cannot be applied either.
Ancillary procurement services are advisory, preparatory and support activities connected with preparing or running a public procurement procedure. Examples include advice on planning or running a procurement procedure, and preparing and running the procedure on behalf of the contracting authority (Kbt. Section 3, point 14). Since 1 January 2025, a contracting authority can buy these services without a procurement procedure up to the EU threshold, that is, within the range of the national procedure. Above that threshold a procurement procedure is required. As an independent public procurement consultancy, we provide this kind of service to contracting authorities, from planning the procedure to running it.
Since 1 February 2024, an organisation otherwise outside the scope of the Kbt. must also run a procurement procedure if it finances a service contract with an estimated value at or above the national threshold directly from European Union funds. The rule applies only to service contracts, not to supplies or works. Funding from the Recovery and Resilience Facility (RRF) is exempt from the rule. The aid intensity does not matter, only the estimated value of the procurement. If the estimated value reaches the national threshold, the procedural rules of the Kbt. apply. Which purchases need a procedure after a successful grant application, and how we run them, is set out on our procurement for grant-funded projects page.
TED (Tenders Electronic Daily) is the European Union's database of official public procurement notices. Its purpose is to give economic operators across the EU market an equal chance to learn about procurements.
Publication is mandatory when the estimated net value of the procurement reaches or exceeds the EU thresholds. This obligation covers:
- the notice launching the procedure,
- the publication of the outcome of the procedure,
- and certain contract modifications.
Failing to publish on TED in a procurement that reaches the EU threshold is an infringement. The KDB may impose a fine and, before the contract is signed, annul the contracting authority's decisions. A contract becomes null and void when the procedure is unlawfully skipped or a procedure without prior publication is used without legal grounds, as explained in this question.
As a rule, the threshold decides whether a national or an EU procedure is run. The exceptions are social and other specific services, which are procured under the national procedure even above the EU threshold, and concessions, which have their own rules. This matters to tenderers too, because the procedure determines the rules that apply to you.
Two things change above the EU threshold:
- Where the notice appears. In the national procedure, in the Public Procurement Bulletin (Közbeszerzési Értesítő). Above the EU threshold, on TED as well. Our tender monitoring service checks the new calls from both sources every week and tells you which ones your company qualifies for.
- How much time you have. The EU procedure generally sets longer minimum time limits for tenders, so there is more time to prepare.
The time limit for a request for review and the standstill period are the same in both procedures. The difference is in the simplified national procedure available for works below HUF 300 million, where both the standstill period and the time limit for a request for review against the decision closing the procedure are 5 days instead of 10.
For the full tendering process, see our service for tenderers.